Our Projects

PROJECTS

Let Rachel bring our Core Values to your
next Project. Integrity. Experience.
Creativity. Safety.

Trunk Utilities to Lake John

Annandale, MN

This public utility project came to life due to the need to extend city sewer and water to the 23 lot Preserve at Lake John Development that Rachel Development will complete Spring of 2024. Rachel utility crews embarked on this journey the second week of June 2023 after road restrictions were lifted. The Rachel Crew was able to complete 12,696 LF of pipe in 8 weeks. This impressive schedule was accompanied with live traffic in both directions along County Road 38 and limited ROW to complete work in. In addition, Rachel crews had to coordinate with Xcel Energy during their transmission line rebuild along the same alignment. Great work done by Team Rachel!

Project Highlights

  • 6402 LF of 8″ Forechain
  • Watermain 6139 LF of 12″
  • 65 LF of 20″ of Steel casing Jack & Bored under County Road 38
  • 96″ Diameter Lift Station Set with Valve vault at a depth of 32′
  • (3) 72″ ARV structures, each being placed at 10′ depth

Completion Date: June 2024

Owner

City of Annandale – Annandale, MN

Engineer

Bolton & Menk, Inc – St. Cloud, MN

Other Projects