Creston Solar is a 50 MW site stretched over 340 acres. The project consisted of site grading for a new solar array, temporary sedimentation ponds, gravel access roads, fencing and final restoration. This solar project is currently on-going but a majority of the work has already been completed during the 2023 season. Creston has been a success thus far due to the on-site field management, the teams previous experience on solar sites, and experience with this construction group in the past.
PROJECT HIGHLIGHTS
Approximately 500,000 CY of dirt to be moved
23,000 Ton of Aggregate Base Import
23,000 LF of Fence Installation